LOOKING FORWARD TO A BRIGHTER TOMORROW
We always find new ways to run our refineries which enables us to operate more safely, reliably and efficiently; reduce costs, recover more resources and better manage risks.
A new state of art unit has been installed to enhance safety & environment with improved mechanical integrity as a replacement of old crude.
Approved Cost:1458 Crores
Benefits of the project:
Commissioning Date: 30th Nov 2015
The use of single Divided Wall Column (DWC) has not only reduced the number of equipment but has also resulted in reduction of steam consumption.
Unit Capacity: 0.62 MMTPA
Approved Cost: Rs. 725 Crores
Commissioning Date: 19th Jan 2017
This project ensured constant supply of BSIV HSD throughout the country to provide cleaner fuel for society and environment as a whole.
Unit Capacity: 2.6 MMTPA
Approved Cost: Rs. Rs. 1714 Crores
The project was completed in 22 Months from date of Environment Clearance which has set a new bench mark in project execution.
Commissioning Date: 27th Jun 2017
This project was initiated to install 0.9 MMPTA capacity unit in order to meet the government mandate of producing 100% BS IV MS with effect from April 2020.
Capacity: 0.9 MMTPA
Approved Cost: Rs. 554 Crores
BPCL plans to diversify into petrochemicals on a long term basis as it aims to provide an attractive higher value addition alternative over transportation fuels. In view of above BPCL Mumbai Refinery is coming up with large CAPEX investment of approx. Rs. 13,000 Crores in the following projects.